전착도장 사업부

전착도장라인 생산공정

  • 01수입검사

    Receiving inspection

  • 02LOADING

    LOADING

  • 03탕세 (DIP),50-60℃

    Hot water cleaning (dip),50-60℃

  • 04예비탈지 (SPRAY) 50-60℃

    Pre-degreasing (spray) 50-60℃

  • 05탈지#1 (DIP), 50-60℃

    Degreasing #1 (dip), 50-60℃

  • 06탈지#2 (DIP), 50-60℃

    Degreasing #2 (dip), 50-60℃

  • 07수세#1 (SPRAY)

    Water cleaning #1 (spray)

  • 08수세#2 (DIP)

    Water cleaning #2 (dip)

  • 09표면조정 (DIP)

    Surface Conditioning(dip)

  • 10화성피막 (DIP) 40-45℃

    Phosphasing (dip) 40-45℃

  • 11수세#3 (SPRAY)

    Water cleaning #3 (spray)

  • 12수세#4 (DIP)

    Water cleaning #4 (dip)

  • 13순수세#1 (DIP)

    D.I water cleaning #1 (dip)

  • 14수절

    Dehydration

  • 15전착도장 (DIP) 30℃±1

    Electrodeposition coating (dip) 30℃±1

  • 16UF#1 (SPRY)

    Ultrafiltration#1 (spray)

  • 17UF#2 (DIP)

    Ultrafiltration#2 (dip)

  • 18UF#3 (DIP)

    Ultrafiltration#3 (dip)

  • 19순수세#2 (SPRAY)

    D.I water cleaning #2 (spray)

  • 20세팅존

    Setting zone

  • 21건조로(LNG) 200℃±10

    Drying (LNG) 200℃±10

  • 22UN-LOADING

    Unloading

  • 23출하 검사

    Shipment inspection

  • 24포장 / 출하

    Packaging / shipping